Departments are still failing to meet their legal obligations to review regulations

Post-implementation reviews (PIRs) are a legal obligation to review and evaluate existing regulations and a critical part of how government demonstrates that regulations are working as intended, or identifies how they can be fixed. However, despite repeated calls over many years and firm commitments from permanent secretaries to address the problem, departments are still failing to get on top of their obligations to complete PIRs on time – four departments still have 6 PIRs outstanding: BIST, DfT, FSA and MHCLG.

In our last PIR blog in May 2026 we reported that progress had stalled, with new PIRs becoming overdue as quickly as departments were completing previous overdue ones. We said that departments needed to complete new PIRs on time as well as managing the backlog – unfortunately they have failed to do this and although there has been a small reduction (from 47 in May to 40 now) far more needs to be done.

Overdue Post-Implementation Reviews by Department

*For data from before the changes in departmental responsibilities in 2026, PIRs for former DBT, DCMS and DSIT have been assigned to current departments based on policy areas.

Post-Implementation Reviews are an important way for the Government to support its growth agenda by identifying regulations that place an excessive burden on businesses and inhibit growth. If done well they should identify opportunities to revise regulations to make them more pro-growth. Given their desire to promote economic growth as well as their legal commitments, we would have expected Government to be more focussed on completing PIRs.

The RPC has been reporting on departments' performance in undertaking PIRs and the backlog of overdue PIRs (those that have not been undertaken by the fifth anniversary of the introduction of the regulation) since the start of 2025. Departments are reminded 12 months in advance of regulations approaching their review date.

A full breakdown of overdue and upcoming PIRs by department is published on our website.

Departments' progress is set out below.

Strong performance

Department for Energy Security and Net Zero (DESNZ)

• In May we challenged DESNZ to complete all remaining PIRs by our next update. We are pleased to announce that DESNZ have done so and now have no PIRs outstanding. We hope they continue to remain on top of their commitments.

Department for Environment, Food and Rural Affairs (DEFRA)

• In May we congratulated DEFRA on having reduced their backlog down to a single PIR. DEFRA is now up to date with all their PIRs due in 2026. We hope they continue to remain on top of their commitments.

Progress made, but more to do

Department for Transport (DfT)

• DfT committed to completing their overdue PIRs by June 2025 - a deadline they missed. Following my letter in December, DfT's permanent secretary wrote to me to say that the department was taking steps to accelerate clearances and recommitted to completing all outstanding PIRs by the end of March 2027.

• Of the 9 PIRs overdue in May 26, 7 have now been completed, and we have been told that one more is awaiting clearance. However, 4 new measures have become overdue since May, leaving a total of 6 overdue measures. All 4 of the new measures have been reviewed by the RPC and are awaiting publication. DfT have done a good job in reducing their backlog and are on track to meet their new commitment. We expect them to keep on top of their statutory deadlines on new PIRs going forward.

HM Treasury (HMT)

• HMT previously committed to completing all overdue PIR’s ‘in due course’. In May we identified 3 overdue PIRs. It has since been confirmed that one of these is reviewed annually by the Financial Policy Committee and another has been completed, leaving only 1 legacy PIR overdue. HMT have informed us this is currently being drafted. One additional PIR has become overdue since May. HMT have informed us that they intend to complete this as part of a wider review of the Financial Services and Markets Act next year. HMT have reduced their backlog and have plans for completing all outstanding PIRs. We expect them to keep on top of their statutory deadlines on new PIRs going forward.

Progress stalled

Department of Health and Social Care (DHSC)

• Last year, DHSC committed to completing their overdue PIRs as soon as possible. After some improvement in the first half of the year, there has been no further progress and 3 PIRs remain overdue. DHSC need to do more and I will write to their permanent secretary to chase progress.

Department for Digital, Culture, Media and Sport (DCMS)

• DCMS was formed in Summer 2026 from DCMS and parts of DSIT. The new department has 3 PIRs overdue. The former DCMS had no overdue PIRs, while DSIT had committed to clear all of their overdue PIRs by April.

• After progress by former DSIT earlier in the year, this is a disappointing result. We expect DCMS to complete the remaining PIRs by our next update; I will write to their permanent secretary to remind them of their statutory obligations.

Disappointing Performance

Department for Business, Innovation, Science and Trade (BIST)

• BIST was formed in Summer 2026 from DBT and parts of DSIT. The new department has 6 overdue PIRs - the joint highest number of any department. DSIT and DBT had both committed to clear all of their overdue PIRs by April.

• The former DBT has cleared all legacy PIRs, however, the department is not keeping up with new commitments, with 4 PIRs outstanding, all of which became overdue in the last year. Both former DSIT PIRs are still overdue from our previous update.

• The Department have informed us that 4 of the 6 overdue PIRs are currently undergoing clearances. I will write to the department’s permanent secretary to remind them of their legal obligations and say that we expect to see significant progress by our next update.

Ministry of Housing, Communities and Local Government (MHCLG)

• MHCLG committed to completing all their backlog by November 2026, however, they still have 6 PIRs outstanding, the same number as in May and the joint highest number of any department.

• The Permanent Secretary wrote to me earlier this month acknowledging that their performance has fallen short of their commitment set out in the Spring. His letter set out the progress the Department is making, with 5 of the outstanding PIRs expected to be completed in November and the sixth in February 2027. I look forward to seeing all of MHCLGs outstanding PIRs being completed by our next update.

Food Standards Agency (FSA)

• In May 2026 the FSA had 6 PIRs overdue and they have made no progress in reducing this number leaving them with the joint highest number of any department.

• In June the Chief Executive of the FSA committed to write to me with a further update in the Autumn. I await her update and expect a firm commitment on completing the outstanding PIRs.

Next steps

If a department currently has any PIRs approaching their review date in the next 12 months, now is the time to act to avoid breaching its legal obligations, obviously if PIRs are already overdue they should be completed as quickly as possible. BIST will continue to collect PIR data from departments at 6 monthly intervals and we will continue to report on departments’ progress.

The RPC secretariat is available to discuss department’s pipelines and answer questions about what a fit-for-purpose PIR looks like. Reach us at: enquiries@rpc.gov.uk.

https://rpc.blog.gov.uk/2026/11/24/departments-are-still-failing-to-meet-their-legal-obligations-to-review-regulations/

seen at 11:37, 24 November in Regulatory Policy Committee.